A quick note this afternoon to flag, using NEMreview v7, that the two emergency generators have started providing first power to the grid, during commissioning:
We expect (we hope!) to see them running very infrequently after commissioning has been completed.
One of three founders of Global-Roam back in 2000, Paul has been CEO of the company since that time.
As an author on WattClarity, Paul's focus has been to help make the electricity market more understandable.
After publishing three Case Studies on Saturday, this 4th Case Study in a long series is much more complex – with 8 different Semi-Scheduled Wind Farm units across VIC and SA exhibiting significant deviations from Target. This Case study looks at April 2016, which is also 3 years after the first 3 case studies.
It’s 1st December 2017 – the first day of summer, and also the promised delivery date for the “world’s largest battery”. In this updated post we look at how it’s been operating.
Does anyone know when the other 7 (or is that 4) units will ne commissioned?
Somewhere the goalposts seem to have shifted from 9 units down to 6 units.
At whose instigation?
From Adelaide Advertiser 2 August 2017
Mr Weatherill has announced plans to lease, and possibly later buy, nine new turbines which can run off either diesel or gas, and provide the state up to 276MW of energy in times of emergency.
Have they fessed up to cost and pool receipts – are they registered participants.?
Does anyone know when the other 7 (or is that 4) units will ne commissioned?
Somewhere the goalposts seem to have shifted from 9 units down to 6 units.
At whose instigation?
From Adelaide Advertiser 2 August 2017
Mr Weatherill has announced plans to lease, and possibly later buy, nine new turbines which can run off either diesel or gas, and provide the state up to 276MW of energy in times of emergency.